Operations at a construction site in Triq L-Akwedott/Triq Fleur De Lys, Birkirkara have been halted by the Building and Construction Agency after works were found to be in breach of the approved method statement.

The BCA said on Monday that enforcement notices have been issued against the  site technical officer and the demolition contractor, with an administrative penalty imposed on both.

It explained that on Tuesday it was informed that heavy machinery was being used to demolish structures at the site. Enforcement officers confirmed that a large excavator with a hydraulic shear attachment was in operation.

The use of such machinery was not included in the method statement and the 
BCA ordered the workers to stop demolition and sealed-off the site. 

Works cannot continue before the fines - which were not disclosed - are settled and it is ensured that the method statement will be followed. 

The BCA was set up in 2019 as new regulations were brought in amid a spate of building collapses caused by the use of heavy machinery on adjoining construction sites.  

Sign up to our free newsletters

Get the best updates straight to your inbox:
Please select at least one mailing list.

You can unsubscribe at any time by clicking the link in the footer of our emails. We use Mailchimp as our marketing platform. By subscribing, you acknowledge that your information will be transferred to Mailchimp for processing.