Those walking along Merchants Street, Valletta, will notice that a tower crane stands at the site where St John’s Co-Cathedral Museum’s tapestry chamber is going to be constructed. The project also includes a spiral staircase and a piston lift that is unique to Malta.

Drilling to place the 170 concrete columns in the foundations that will protect the historical rubble fills.Drilling to place the 170 concrete columns in the foundations that will protect the historical rubble fills.

Although not much is visible to the public, a large amount of work and intense preparations are being carried out. The St John Co-Cathedral Foundation’s consultants, AP Valletta and EM Architects are working together to complete this project.

Geological tests were carried out to ensure the foundations on which the tapestry chamber will be built were adequate. To ensure that this will be up to the current standards, the ground will be strengthened with a wall consisting of concrete columns driven into the ground in specific areas. Many more studies and structural engineering input was necessary.

In all, 170 concrete columns will be placed into the foundations that will protect the historical rubble fills that were once a burial ground. Extensive research and investigations were conducted to ensure that no historical material was lost.

A new entrance will separate the museum from the church

A large amount of work and intense preparations are being carried out for the new museum project.A large amount of work and intense preparations are being carried out for the new museum project.

For the past two years, excavation, all done by hand, was carried out by a group of archaeologists under the supervision of the Superintendence of Cultural Heritage (SCH), who has been providing guidance to integrate and protect any findings.

The project of restoring and constructing new areas entails interventions in one of Malta’s most historically important monuments. Continuous discussions are held with the Planning Authority, the Superintendence of Cultural Heritage, Valletta local council, Transport Malta and the shop owners’ association in Valletta.

In this way, all the decisions taken and adjustments made to the existing fabric are carried out with utmost care and based on in-depth research and investigations to ensure sound knowledge of the site. Any changes to the original permit are subject to the approval of the Superintendence of Cultural Heritage, the Planning Authority and UNESCO.

Coring tests being carried out.Coring tests being carried out.

The new foundations and the construction of the tapestry chamber and other restoration works were entrusted to AX Construction Ltd and commenced last April. Significant progress has been recorded to date, with the installation of steel reinforcement for the stabilising columns before applying the concrete cast.

As investigations were being carried out, tenders for works on the area to house the Caravaggio Wing were initiated.

The ground floor consists of a hall that will exhibit the painting depicting St Jerome by Caravaggio and the audio-visual space that will project the story of the artist and his stay on the island as well as a hall that will project the famous painting by Caravaggio, The Beheading of St John the Baptist. The works have reached completion and the wing will be opened shortly.

Caravaggio’s St Jerome will be exhibited in a hall on the museum’s ground floor.Caravaggio’s St Jerome will be exhibited in a hall on the museum’s ground floor.

A view of the tower crane installed at the site where St John’s Co-Cathedral Museum’s tapestry chamber is going to be constructed.A view of the tower crane installed at the site where St John’s Co-Cathedral Museum’s tapestry chamber is going to be constructed.

The restoration of the crypt below the oratory and the basement spaces will soon start.

Together with the Caravaggio Wing, the rehabilitation of these areas is part-financed by the European Regional and Development Fund.

The aim of the new museum is to utilise the buildings adjacent to the co-cathedral to accommodate the artefacts currently kept in storage.

The extension works include the rehabilitation of the existing areas within the basement level, the restoration of the Bartolott Crypt, the construction of a new tapestry chamber, the Caravaggio Wing and a new entrance/ exit and ticketing area from Merchants Street that will separate the museum from the church.

Sign up to our free newsletters

Get the best updates straight to your inbox:
Please select at least one mailing list.

You can unsubscribe at any time by clicking the link in the footer of our emails. We use Mailchimp as our marketing platform. By subscribing, you acknowledge that your information will be transferred to Mailchimp for processing.